Installation typically starts with a vertical mullion at one end of the curtain wall assembly.
Curtain wall installation sequence.
These are unitized or modular systems figure 9 2a b and stick systems figure 9 3a b in the stick system the curtain wall frame mullions and glazing panels are installed and connected together piece by piece.
Prior to hanging the frames the delivered crates are opened and inspected then laid horizontally on movable dollies and.
Installation method statement for aluminium cladding.
Install slide n pivot jamb anchor after cassette frame assembly.
United states aluminum series 4500 curtain wall installation instructions page 5 d5 the series 4500 curtain wall systems are designed for shear block stick erected and screw spline panel erected type assembly methods the shear block method of assembly is recommended for multi floor applications where mullions will be spliced.
Curtain wall to the other end of the rough opening.
By no means is this the only technique of assembling a wall but this section covers the steps necessary to install a stick wall and a unitized wall.
Step 1 5 step 1 6 1 preparation 5 curtain wall.
3 each cassette type has its own sequence of pages for size determination to installation phase.
Available in a variety of depths profiles finishes and unitized options our relatively lightweight weathertight curtain wall systems provide a cutting edge combination of design and performance including thermal hurricane and blast resistance.
2 field verify dlo of installed curtain wall prior to cassette frame machining and assembly.
What follows is a generalization of the procedures involved with erecting a curtain wall system.
The installation duration for each floor is tied to the embed anchor installation and concrete pour.
For aluminum cladding adjoining the glazed curtain wall the same procedure for survey and leveling has to be followed before installation.
If the unit has a corner start at the corner.
To install fire insulation according to approved shop drawing at top part of concrete beam surface prior to curtain wall installation.
Aluminum brackets will be fixed on the concrete or hollow block by using applicable anchor bolts as per the drawing.
4 cassette frames can be installed in vertical runs horizontal runs or shingled.
Stick wall installation sequence establish control lines.
Curtain walls generally fall into two basic categories that are based on their method of fabrication and installation.